CHAPTER 5 DEEP FOUNDATION (2)7788788.ppt

[ad_1]

CHAPTER 5 DEEP FOUNDATION (2)7788788.ppt

 Those that transfer the load at a point far
below the substructure.
 Deep foundation are used when adequate soil
capacity is not available close to the surface
and loads must be transferred to firm layers
substantially below the ground surface.
 The common deep foundation system for
buildings are caissons and piles.

CHAPTER 5 DEEP FOUNDATION (2)7788788.ppt

  • 2.  Those that transfer the load at a point far
    below the substructure.
     Deep foundation are used when adequate soil
    capacity is not available close to the surface
    and loads must be transferred to firm layers
    substantially below the ground surface.
     The common deep foundation system for
    buildings are caissons and piles.
  • 3.  A pile can be defined as a column inserted in the
    ground to transmit the structural loads to a
    lower level of subsoil.
     The construction process of pile can be broadly
    characterised by the installation and testing.
     However, there are many proprietary types of
    piles and the testing process for each type
    differed.
     Pile may be classified by the way there are
    formed i.e. Displacement piles (END BEARING)
    and non displacement piles (FRICTION).
  • 4.  Pile may be classified as either End bearing
    or Friction piles, according to the manner in
    which the pile loads are resisted.
     However, in actual practice, virtually all piles
    are supported by a combination of skin
    friction and end bearing.
  • 5.  The shafts of the piles act as columns
    carrying the loads through the overlaying
    weak subsoils to firm strata into which the
    pile to has penetrated.
     This can be rock strata or a layer of firm
    sand or gravel which has been compacted by
    the displacement and vibration encountered
    during the driving.
  • 7.  Any foundation imposes on the ground a
    pressure which spreads out to form a
    pressure bulb.
     If a suitable load bearing strata cannot be
    found at an acceptable level, particularly in
    stiff clay soils, it is possible to use a pile to
    carry this pressure bulb to a lower level
    where a higher bearing capacity is found.
     The friction or floating pile is mainly
    supported by adhesion or friction action of
    the soil around the perimeter of the pile
    shaft.
  • 9. Types of Piles
    Large
    displacement Small displacement Non displacement
    Preformed solid or
    hollow, closed at the
    bottom end driven into
    the ground and left in
    position
    Formed in-situ by driving
    a closed-ended tubular
    section to form a void,
    and then filling the void
    with concrete by
    withdrawing the section
    Steel sections,
    includes H-piles,
    open ended
    tubes and box-
    piles
    Screw-piles A void is formed by
    boring or excavation,.
    The void is filled with
    concrete. The sides of
    the voids are:
    Supported Unsupported
    Permanently
    (by casing)
    Temporarily
    Solid Hollow
    Various
    Systems
    (closed at bottom and
    filled or unfilled after
    driving)
    Timber
    Precast
    Steel tubes or box-piles
    Concrete tubes
    By casing
    By drilling mud
  • 10.  Displacement piles refer to piles that are
    driven, thus displacing the soil, and include
    those piles that are preformed, partially
    preformed or cast in place.
     This is the most cost efficient piling method
    but may not be suitable for areas sensitive to
    noise, vibration and dust.
     The present of boulders can also hinder the
    use of driving piles.
  • 11.  Types of Displacement piles:-
    1) Precast reinforced concrete piles
    2) Steel preformed piles
    3) Composite piles
    4) Driven in situ/Cast-in-Place piles
  • 12.  Come in different sizes and lengths, they are
    driven by drop hammers using a piling rig.
     They provide high strength and resistance to
    decay.
     They are however heavy, and because of its
    brittleness and low tensile strength, cares in
    handling and driving is required.
     Cutting requires the use of pneumatic
    hammers, cutting torches, etc.
  • 16.  H-piles or universal steel beam in the form of
    wide-flange is commonly used.
     They do not cause large displacement and is
    useful where upheaval of the surrounding
    ground is a problem.
     There are capable of supporting heavy loads,
    can easily cut and can be driven to great
    depth.
     The driving method for steel piles is similar
    to that of precast reinforced concrete piles.
  • 17.  The handling and lifting of a steel pile is less
    critical due to its high tensile strength.
     Lengthening of steel piles is through welding.
     Care must be taken in the welding of joints
    to ensure that they are capable of
    withstanding driving stresses without failure.
     A protective steel guard should be welded at
    the joints when necessary.
  • 19.  Also referred to as partially preformed piles,
    composite piles combine the use of precast
    and in situ concrete and/or steel.
     They are an alternative to bored and
    preformed piles for sites with the presence
    of running water or very loose soils.
     The common generic types are the shell piles
    and cased piles
  • 21.  The pile shaft is formed by using a steel tube
    which is either top driven or driven by means
    of an internal drop hammer working on a
    plug of dry concrete/gravel as in Franki
    piles.
     Piles up to 610mm can be constructed using
    this method.
  • 22.  With temporary casing, as the casing is
    withdrawn during the placing/compacting of
    concrete, precautions need to be taken when
    working at depth with groundwater
    movement to prevent problems associated
    with necking (narrowing) caused when the
    groundwater washes away some of the
    concrete thus reducing the effective
    diameter of the pile shaft and consequently
    the concrete cover.
  • 24.  Sometime referred to as replacement piles
    but more commonly as bored pile.
     They are formed by boring/removing a
    column of soil and replaced with steel
    reinforcement and wet concrete cast through
    a funnel or tremie pipe.
     For soft grounds and where the water table
    is high, bentonite may be used during boring
    to resist the excavation and water inflow
    before casting.
  • 25.  Bored piles are considered for sites where
    piling being is being carried out in a close
    proximity to existing buildings where
    vibration, dust and noise need to be
    minimised.
  • 26.  Superstructure design
    Site area
     Soil condition
     Surrounding buildings and structures
     Availability of equipment and site constraints
  • 28.  Pile are driven by drop hammers using a
    piling rig.
     Hammer will be drop to pile head with
    allowable height that have been determine
    until it reach ‘set’ (pile has reach the hard
    strata).
  • 29. 1. Set out the position of each pile and
    establish the temporary benchmarks (TBM)
    on site to determination of cut-off levels of
    piles.
    2. Check the verticality of the piling rig using
    a plumb or spirit level.
    3. Provide markings along the pile section to
    enhance recording of penetration and to
    serve as rough guide to estimate the set
    during driving.
  • 30. 4. Install mild steel helmet. protect pile
    head/joint plate with packing or cushioning
    within e.g. a 25 mm thick plywood between
    the pile head and helmet.
    5. Hoist up and place the pile in position
    5. Check on verticality regularly
    6. Proceed with the hammering. Monitor pile
    penetration according to the markings on
    pile. When the rate of penetration is low,
    monitor pile penetration over 10 blows.
  • 31. Hold one end of a pencil supported firmly
    on a timber board not touching the pile.
    The other end of the pencil marks the pile
    displacement on a graph paper adhered on
    the pile over 10 blows.
    8. Stop piling if the displacement is less than
    the designed displacement over 10 blows.
    Otherwise, continue with the piling
    process.
  • 32. 8. Lengthening of pile can be done by means
    of a mild steel splice sleeve and a dowel
    inserted in and drilled through the centre
    of the pile.
    9. The connection is sealed by welding the
    pile head/joint plate which are pre-
    attached to both ends of a pile in
    manufacturing process.
  • 33. 1. Heavy steel casing is closed at the end
    with a plug of dry concrete
    2. Plug of concrete, driven with a drop
    hammer, expands, grips the sides of the
    casing and takes the casing into the
    ground.
    3. On reaching the required depth the
    casing is restrained by cables and the
    plug of concrete is driven out into the
    ground to form a bulb at the end of the
    pipe
  • 34. 4. Cage or reinforcement is placed
    5. Casing is filled with concrete as the
    casing is withdrawn
  • 37.  This is a new technique used for the
    installation of pile.
     Using hydraulic machine to inject the pile
    into the ground until the pile reach the
    require depth.
     The depth required is base on the working
    load, this can be determine by reading
    pressure on the dial gauge.
     Example, if the pile working load are 12
    tones, the ‘set’ taken will be 24 tones which
    is double from the working load.
  • 39.  This method uses a vibro hammer to install
    the pile into ground.
     The vibro hammer will hold the pile head
    and transfer the vibration to the end of the
    pile toe.
     The vibration will then be transferred to the
    ground and the shear strength of the soil is
    reduced.
     This will enable the pile to be installed into
    the ground using the vibro hammer and the
    pile own weight.
     This method is suitable to be used on soft
  • 41.  This method is using excavation machine
    which are percussion or rotary.
     The hole are formed by boring/removing a
    column of soil and replaced with steel
    reinforcement and wet concrete cast through
    a funnel or tremie pipe.
     This method are used for bored pile and
    micro pile.
  • 44.  Piles are generally driven closely together in
    clusters that contain from two to twenty-five
    piles each
     The piles in each cluster are later joined at the
    top by a reinforced concrete pile cap, which
    distributes the load of the column or wall
    equally among the piles
     Clusters of two, three, four and nine piles with
    their concrete caps. The caps are reinforced to
    transmit column loads equally into all the piles
    in the cluster
  • 46.  The main objective of forming test piles is
    to confirm that the design and formation of
    the chosen pile type is adequate.
     Pile load tests give information on the
    performance of the pile, installation
    problem, lengths, working loads and
    settlements.
  • 47.  Static load tests involve the use of a heavy
    load or reaction method to counter the
    application of an axial load to the top of the
    test pile using one or more hydraulic jacks.
     The main objectives of static load test are:-
    1. to determine the ultimate failure load
    2. capability of supporting a load without
    excessive or continuous displacement
    3. to verify that the allowable loads used for
    the design of a pile are appropriate and
    that the installation procedure is
    satisfactory.
  • 48.  Two types of loading are commonly used:-
    i. Maintained load test
     also referred to as working load test, which
    load is increased at fixed increment up to
    1.5 to 2.5 times its working load.
     settlement is recorded with respect to
    time of each increment.
     when the rate of settlement reaches,
    maintain the load for 12 hours.
  • 49. ii. Ultimate load test
     The pile is steadily jacked into the ground
    at a constant rate until failure.
     The ultimate bearing capacity of the pile is
    the load at which settlement continues to
    increase without any further increase of
    load or the load causing a gross settlement
    of 10% of the pile diameter.
  • 50.  This is only applied to test piles which must
    not be used as part of the finished
    foundations but should be formed and tested
    in such a position that will not interfere with
    the actual contract but is nevertheless truly
    representative of site conditions.
  • 52.  Dynamic load test is an direct method using
    the wave propagation theory to estimate the
    condition of a hammer-pile-soil system.
     The method involves the process of
    impacting the tested pile with a large drop
    weight and measuring the compressive stress
    wave travelling down the pile.
     Transducers and accelerometers are installed
    near the top of the pile to measure the
    reflected wave.
  • 53.  Using measurements of strain and
    acceleration and principles of wave
    mechanics, performance such as static pile
    capacity and pile integrity can be estimated.
  • 55.  Sheet piling comprises a row of pile which
    interlock with one another to form a
    continuous wall which may be temporary or
    permanent.
     It consists of rolled steel sections with
    interlocking edge joints.
     The interlocking edges allow each sheet pile
    to slide into the next relative ease, and
    together they form a steel sheet wall that
    serves the purpose of retaining the soil and
    to some extent, exclusion of ground water.
  • 56.  The standard length of sheet pile is 12m.
    Longer piles are achieved by joining sections
    together by either welding or splicing or
    both.
  • 57. 57
    Z-Type (Z)
    Used for
    intermediate to deep
    wall construction
    Larson / “U” Type (U)
    Used for applications similar to Z –
    Type
    Flat / Straight Type (SA), (S)
    Used for filled cell construction
    Arch shaped & lightweight
    Used for shallower wall construction
  • 58. 58
    Typical types
    of interlocks
    Ball
    & Socket (BS)
    Single Jaw (SJ)
    Double Jaw (DJ)
    Hook & Grip (HG)
    Thumb & Finger
    one point contact (TFX)
    Double Hook (DH)
    Thumb & Finger
    three point contact (TF)

[ad_2]

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More